Where the construction contract does not comply with the requirements of the Construction Contracts Act 2013 (“CCA”), the CCA provides that the Schedule applies.
In Section 3, the CCA provide that the Schedule provides a different regime depending upon whether you are the Main Contractor or a Sub-Contractor.
Main Contractor
Section 3 (3) The Schedule shall apply to a main contract if and to the extent that it does not make provision for the matters specified in subsections (1) and (2).
Payment claim dates
Schedule - Paragraph 1
The payment claim dates under a construction contract shall (subject to paragraph 2) be as follows:
(a) 30 days after the commencement date of the construction contract;
(b) 30 days after the date referred to in clause (a) and every 30 days thereafter up to the date of substantial completion;
(c) 30 days after the date of final completion.
Schedule - Paragraph 2
Where a construction contract provides, or the parties to a construction contract otherwise agree, that the duration of the work under the construction contract is or is estimated to be less than 45 consecutive days, the payment claim date shall be 14 days following completion of the work under the construction contract.
Payment due date
Schedule - Paragraph 3
The date on which payment is due in relation to an amount claimed under a construction contract shall be no later than 30 days after the payment claim date.
Calculation of the amount due
Schedule - Paragraph 4
The amount of an interim payment under a construction contract shall (subject to paragraph 5) be the difference between—
(a) the aggregate of the gross value (determined in accordance with the construction contract) of the work done under the construction contract at the payment claim date concerned together with any additional amounts in the interim payment under the construction contract, less any deductions from payment provided for by the construction contract, and
(b) the aggregate amount of interim payments that have already been made at that payment claim date.
Schedule – Paragraph 5
The aggregate of payments made under a construction contract shall not exceed—
(a) the amount provided for in the construction contract as originally concluded, and
(b) amounts provided for by any amendments to that contract agreed between the parties.